Sidi Cheho Al Massira Hydropower Project
Morocco
Borrower | Morocco |
Financing Type | Public Sector |
Instrument | Project Loan |
Focus Area | Energy |
Approved | 02.08.1977 |
Signed | 06.10.1977 |
Status | Completed |
Loan Administrator | IBRD |
Executing Agency | Office National de l'Electricité |
Co-financiers | IBRD |
OPEC Fund Contribution (US$m) | 3.00 |
Total Project Cost (US$m) | 167.10 |
The project sought to contribute to the rational development of water resources in the Oum-er-R'bia basin and to meeting the growing demand for electric power, industrial and potable water and water for irrigation development through the construction of: (a) the Al-Massira dam at Sidi Cheho; (b) a 120 MW power station with an adjacent 225 kV substation; (c) about 200 km of 225 kV transmission lines; and through the preparation of preliminary designs and bid documents for the Merifa dam and power station.