Upolu Emergency Power Project
Samoa
| Borrower | Samoa |
| Financing Type | Public Sector |
| Instrument | Project Loan |
| Focus Area | Energy |
| Approved | 13.06.1991 |
| Signed | 25.10.1991 |
| Status | Completed |
| Loan Administrator | ADB |
| Executing Agency | Electric Power Corporation (EPC) |
| Co-financiers | IDA, ADB, Government |
| OPEC Fund Contribution (US$m) | 1.70 |
| Total Project Cost (US$m) | 4.44 |
This project was conceived to repair some of the damage caused to Samoa’s power sector by two severe tropical cyclones. It provided for the procurement and installation of a new diesel generator, as well as for renovation works at several seriously damaged hydro and diesel power generation plants. The project sought to restore the country’s generating capacity to pre-cyclone levels and bring an end to two-years of power shortages.