Three Hydroelectric Power Stations Rehabilitation Project
Rwanda
| Borrower | Rwanda |
| Financing Type | Public Sector |
| Instrument | Project Loan |
| Focus Area | Energy |
| Approved | 10.12.2002 |
| Signed | 04.02.2003 |
| Status | Completed |
| Loan Administrator | OPEC Fund |
| Executing Agency | Rwanda Energy Group (REG) |
| Co-financiers | BADEA, Government |
| OPEC Fund Contribution (US$m) | 5.00 |
| Total Project Cost (US$m) | 11.30 |
The project will rehabilitate three dilapidated hydroelectric power plants in the western provinces of Ruhengeri and Gisenyi. Works to be carried out include:
- renovation and modernization of each plant;
- repair of connecting canals;
- carrying out of erosion and flood protection measures to prevent damage to the powerhouses at the plants;
- construction of access roads and workshops; and
- implementation of capacity-building schemes.