We use Cookies. Read our Terms
- Operations
- Third Power Project
Third Power Project
Sierra Leone
Borrower | Sierra Leone |
Financing Type | Public Sector |
Instrument | Project Loan |
Focus Area | Energy |
Approved | 23.03.1979 |
Signed | 21.05.1979 |
Status | Completed |
Loan Administrator | IDA |
Executing Agency | Sierra Leone Electricity Corporation |
Co-financiers | IDA, BADEA, Governement |
OPEC Fund Contribution (US$m) | 1.60 |
Total Project Cost (US$m) | 16.80 |
The project comprises the following components: (a) installation of a 9.2 MW low-speed diesel engineering unit at the King Tom power plant and construction of priority 33 kV distribution facilities in Freetown; (b) expansion of the generating capacity in ten provincial centres; (c) supply of data processing equipment; (d) technical assistance; and (e) consultant services to complete the feasibility study of the Bumbuna hydroelectric scheme and design studies to tender the construction of the hydro plant's first stage.