Second Bombay High Offshore Development
India
Borrower | India |
Financing Type | Public Sector |
Instrument | Project Loan |
Focus Area | Energy |
Approved | 28.01.1981 |
Signed | 16.03.1981 |
Status | Completed |
Loan Administrator | IBRD |
Executing Agency | Oil and Natural Gas Commission (ONGC) |
Co-financiers | IBRD, Government |
OPEC Fund Contribution (US$m) | 30.00 |
Total Project Cost (US$m) | 823.20 |
The project consists of the drilling of 64 directional development wells; construction and installation of 15 simple four-let well platforms; one three-deck, eight-leg processing platform with 180,000 bbl/day capacity; and a four-leg two deck living quarters platform; installation of 133 km of 8"-20" sub-sea flow lines; additional shore facilities; telemetry and telecontrol facilities, and consulting services.