Second Accelerated Rural Electrification
Thailand
Borrower | Thailand |
Financing Type | Public Sector |
Instrument | Project Loan |
Focus Area | Energy |
Approved | 30.09.1980 |
Signed | 24.10.1980 |
Status | Completed |
Loan Administrator | IBRD |
Executing Agency | Provincial Electricity Authority (PEA) |
Co-financiers | IBRD, SFD, Gvt. of Norway, PEA |
OPEC Fund Contribution (US$m) | 8.00 |
Total Project Cost (US$m) | 270.00 |
The project constitutes the second phase of the PEA Accelerated Rural Electrification Program. It comprises the electrification of 7,878 villages, as well as a feasibility study on mini-hydro schemes and consultancy services for the PEA. The project will benefit an estimated 6 million rural poor through increased agricultural productivity and an improved quality of life and will reduce the country's dependence on imported energy through diversification away from kerosene and diesel oil.