Rehabilitation and extension of Bambari & Bozoum Water Supply and Sewerage Systems Project
Central African Republic
| Borrower | Central African Republic |
| Financing Type | Public Sector |
| Instrument | Project Loan |
| Focus Area | Water & Sanitation |
| Approved | 05.10.2011 |
| Signed | 07.03.2012 |
| Status | Cancelled |
| Loan Administrator | BADEA |
| Executing Agency | Ministry of Mining Energy and Hydraulics |
| Co-financiers | Government, BADEA |
| OPEC Fund Contribution (US$m) | 4.00 |
| Total Project Cost (US$m) | 13.00 |
To help address drinking water shortages and improve sanitation services for roughly 74,000 people in the cities Bozoum and Bambari. Works to be carried out include:
- rehabilitation of existing water treatment plant and construction of a new one;
- rehabilitation of water production, storage, transportation and distribution infrastructure;
- construction of a power station;
- drilling of wells and boreholes;
- construction of pipelines, drainage systems and public latrines;
- provision of maintenance equipment; and,
- consultancy services.