Mukungwa Hydro-Electric Project
Rwanda
| Borrower | Rwanda |
| Financing Type | Public Sector |
| Instrument | Project Loan |
| Focus Area | Energy |
| Approved | 16.11.1977 |
| Signed | 15.12.1977 |
| Status | Completed |
| Loan Administrator | BADEA |
| Executing Agency | Ministry of Public Works and Equipment |
| Co-financiers | EDF, BADEA, Government |
| OPEC Fund Contribution (US$m) | 2.35 |
| Total Project Cost (US$m) | 34.46 |
The project consisted of: (a) construction of the dam; (b) construction of the off-take comprising a thin grate and safety valve; (c) construction of a supply system; (d) supply and installation of the power plant (two groups of alternating turbines of 6.35 MW each); (e) construction fo 70/100 kV and 30 kV lines for the connection to the national network.