Mokha Power Station Project
Yemen
Borrower | Yemen |
Financing Type | Public Sector |
Instrument | Project Loan |
Focus Area | Energy |
Approved | 16.06.1982 |
Signed | 28.07.1982 |
Status | Completed |
Loan Administrator | AFESD |
Executing Agency | Yemen General Electric Corporation (YGEC) |
Co-financiers | AFESD, KFAED, SFD, Bilateral/Suppliers , Government |
OPEC Fund Contribution (US$m) | 10.00 |
Total Project Cost (US$m) | 351.60 |
The project provides for the construction of a new steam power station in the southern part of the country, which will be connected to the national grid. The project will help ensure a reliable power supply to the region and will contribute to the development of a fast-growing area in terms of agriculture, industry and urbanization.