Mini Hydropower Project
Nepal
Borrower | Nepal |
Financing Type | Public Sector |
Instrument | Project Loan |
Focus Area | Energy |
Approved | 23.06.1981 |
Signed | 15.09.1981 |
Status | Completed |
Loan Administrator | ADB |
Executing Agency | Small Hydro-Development Board |
Co-financiers | ADB, UNOPS, Government |
OPEC Fund Contribution (US$m) | 4.00 |
Total Project Cost (US$m) | 15.15 |
The project is expected to benefit around 250,000 people living in 15 major potential growth centers in hill districts and 46 adjoining villages. Works will include:
- construction of eight mini hydroelectric power stations, including associated transmission, distribution, service connections;
- provision of amaintenance workshop and training facilities; and
- consultancy services.