Hodeida Sanitation Project
Yemen
| Borrower | Yemen |
| Financing Type | Public Sector |
| Instrument | Project Loan |
| Focus Area | Water & Sanitation |
| Approved | 06.11.2001 |
| Signed | 26.04.2002 |
| Status | Completed |
| Loan Administrator | OPEC Fund |
| Executing Agency | Min. of Electricity and Water |
| Co-financiers | Government |
| OPEC Fund Contribution (US$m) | 12.00 |
| Total Project Cost (US$m) | 14.25 |
Sanitation coverage in Yemen's western city of Hodeida is low, with only around one-half of its 420,000-strong population connected to the network. Parts of the city's wastewater system have collapsed or become blocked, necessitating the use of above-ground sewage lines. The project will carry out the following:
- replacement 15-km of main sewer lines;
- installation of 230 solid manhole covers to prevent sand intrusion;
- rehabilitation of three pumping stations, including new power systems and standby generators.