- Gode-Kebridehar 132kV Power Transmission
Gode-Kebridehar 132kV Power Transmission
Ethiopia
| Borrower | Ethiopia |
| Financing Type | Public Sector |
| Instrument | Project Loan |
| Focus Area | Energy |
| Approved | 21.12.2011 |
| Signed | 08.03.2012 |
| Status | Completed |
| Loan Administrator | OPEC Fund |
| Executing Agency | The Ethiopia Electric Power Corporation (EEPCo) |
| Co-financiers | BADEA, SFD, GOE |
| OPEC Fund Contribution (US$m) | 15.00 |
| Total Project Cost (US$m) | 46.12 |
To expand the existing national grid by extending the distribution and transmission lines to the villages and towns in the project area. Works will include:
- construction of a 132kV, single circuit transmission line and 132/33kV substation at Kebridehar;
- construction of a 33kV distribution line;
- installation of distribution transformers; and
- consultancy services.