| Borrower | Yemen |
| Financing Type | Public Sector |
| Instrument | Project Loan |
| Focus Area | Transportation |
| Approved | 18.11.1986 |
| Signed | 11.05.1987 |
| Status | Completed |
| Loan Administrator | ISDB |
| Executing Agency | Highway Authority (HA) under the Ministry of Public Works |
| Co-financiers | ISDB, Government |
| OPEC Fund Contribution (US$m) | 5.00 |
| Total Project Cost (US$m) | 11.90 |
The project will carry out the following:
- construction of a 56.4 km-long paved roadfrom Fardah to Al-Hazm;
- construction of an embankment; and
- consultancy services.