Chiew Larn Hydroelectric Project
Thailand
| Borrower | Thailand |
| Financing Type | Public Sector |
| Instrument | Project Loan |
| Focus Area | Energy |
| Approved | 23.06.1981 |
| Signed | 18.09.1981 |
| Status | Completed |
| Loan Administrator | IBRD |
| Executing Agency | Electricity Generating Authority of Thailand (EGAT) |
| Co-financiers | IBRD, KFAED, EGAT |
| OPEC Fund Contribution (US$m) | 21.80 |
| Total Project Cost (US$m) | 181.30 |
The project is part of a government power development program designed to reduce the country's dependence on imported oil through the development of its indigenous energy resources. The project consists of the construction of a rockfill dam, an open spillway, an intake structure, a surface powerhouse (with three 80 MW generating units); the installation of 230 kV and 115 kV double circuit transmission lines; and a resettlement program for 315 families living in the reservoir area.