Bombay High Offshore Development (Phase 1) Project
India
| Borrower | India |
| Financing Type | Public Sector |
| Instrument | Project Loan |
| Focus Area | Energy |
| Approved | 16.11.1977 |
| Signed | 16.12.1977 |
| Status | Completed |
| Loan Administrator | IBRD |
| Executing Agency | Oil and National Gas Commission (ONGC) |
| Co-financiers | IBRD, Government |
| OPEC Fund Contribution (US$m) | 14.00 |
| Total Project Cost (US$m) | 571.00 |
The works include development driling at Bombay High North and Bassein and the erection of the necessary well platforms, 209 km sub-sea gathering lines connected to the 3 main processing platforms, an on-shore terminal, supply lines and a supply base for the off-shore installations, telecommunications and a control system to cover the entire Bombay High Program.
The project is intended to assist India in becoming self-sufficient in petreoleum.