- Ar re-gga Deir Ez-zoor Hassaka Road Project
Ar re-gga Deir Ez-zoor Hassaka Road Project
Syria
| Borrower | Syria |
| Financing Type | Public Sector |
| Instrument | Project Loan |
| Focus Area | Transportation |
| Approved | 16.12.2008 |
| Signed | 28.04.2009 |
| Status | Completed |
| Loan Administrator | KFAED |
| Executing Agency | Public Establishment for Road & Communication |
| Co-financiers | Government, KFAED |
| OPEC Fund Contribution (US$m) | 30.00 |
| Total Project Cost (US$m) | 188.58 |
Project works will taka place in the agriculturally-rich regions of Ar-regga, Deir ez-zoor and Hassaka and will include:
- construction of a 308 km-long road;
- construction of a 380 m overpass bridge over the Euphrates River;
- installation of drainage works to prevent flooding; and
- paving of around 25 km of roads that will connect the new road with surrounding towns and villages.