Andekaleka Hydroelectric Project (Phase II)
Madagascar
| Borrower | Madagascar |
| Financing Type | Public Sector |
| Instrument | Project Loan |
| Focus Area | Energy |
| Approved | 20.09.2005 |
| Signed | 21.12.2005 |
| Status | Completed |
| Loan Administrator | BADEA |
| Executing Agency | Electricity and water Corporation (JIRAMA) |
| Co-financiers | BADEA, KFAED, GOVT |
| OPEC Fund Contribution (US$m) | 6.50 |
| Total Project Cost (US$m) | 26.80 |
The project aims at increasing electric power generation capacity at the Andekaleka plant by installing a third hydroelectric turbine. About 7,000 electricity meters to measure electricity consumption are to be procured and installed to help the executing agency to better collect its electricity revenues.