We use Cookies. Read our Terms
- Operations
- Maseru International Airport Project
Maseru International Airport Project
Lesotho
Borrower | Lesotho |
Financing Type | Public Sector |
Instrument | Project Loan |
Focus Area | Transportation |
Approved | 25.06.1979 |
Signed | 28.08.1979 |
Status | Completed |
Loan Administrator | KFAED |
Executing Agency | Ministry of Works |
Co-financiers | ABUDF, AFDB, EDF, KFAED, SFD, Government |
OPEC Fund Contribution (US$m) | 3.00 |
Total Project Cost (US$m) | 43.95 |
The project comprised the first phase development of an international airport, Thota-ea-Mali, consisiting a civil works (construction of runway, apron, approach road), drainage and ancillary works; buildings (terminal, control tower, administrative block, rescue and service buildings); airfield lifting and field cabling; navigational aid and communications; fire and rescue vehicles; and supervision of above works.