We use Cookies. Read our Terms
- Operations
- Andekaleka Hydroelectric Power Project
Andekaleka Hydroelectric Power Project
Madagascar
Borrower | Madagascar |
Financing Type | Public Sector |
Instrument | Project Loan |
Focus Area | Energy |
Approved | 23.03.1979 |
Signed | 18.05.1979 |
Status | Completed |
Loan Administrator | KFAED |
Executing Agency | Malagasy Electricity and Water Corporation (JIRAMA) |
Co-financiers | SFD, ABUDF, KFAED, Government (JIRAMA), Swedish ExportCredit, BADEA, CCCE, CIDA, IDA |
OPEC Fund Contribution (US$m) | 6.50 |
Total Project Cost (US$m) | 116.30 |
1. The project includes: (a) a concrete diversion dam and and intake structure; (b) a tunnel; (c) an underground powerhouse with provision for four 28 MW units and tailrace and access tunnels; (d) two Francis turbines and two generators with a nominal rating of 28 MW each;(e) associated auxilliary electricity and mechanical equipment; (f) a 138-kV, 150-km transmission line to Antananarivo; (g) engineering services. 2. Preliminary investigation and design for storage reservoir of 400-500 million m3 capacity. 3. Technical assistance and training